How to measure for a farm building

You need a long tape or a measuring wheel, a few pegs, a ball of string and a phone. Four sizes and six photos are enough to draw the pack without a site visit, and this is how to take them.

How to measure for a farm building

The four sizes

As on the farm buildings pack. Letters match the sketch.

  1. AThe length and width you want
  2. BHeight to the eaves, under the roof edge
  3. CDoors: how many, how wide, how high
  4. DHow far the ground falls across the site
ABCD

The four sizes, and where the tape goes

A is the length and width you want. Peg the four corners of the footprint, then measure both long sides and both ends. Measure the two diagonals as well. If they match, the pegged shape is square. If they differ, send both figures and we will draw what you measured. Say whether the figures are inside clear space or outside the cladding: a frame and its sheets take space off a clear width, and people often give the clear figure when they mean the outside one. Width is the span across the roof; length runs along the ridge.

B is the height to the eaves, under the roof edge. Measure from the finished yard level at the wall line up to where the roof sheet meets the wall. Work it back from the tallest thing that has to go inside: a tipper with its body raised, a loader with its arm up, a combine with its auger folded. Measure that machine, not the brochure, and add the clearance you want.

C is the doors: how many, how wide, how high. Give the clear opening, not the size of the leaf or the track. Say which wall each door is in. A sliding door needs a free length of wall beside the opening for the leaf to run along, so tell us about anything that sits there: a water trough, a gatepost, a hedge.

D is how far the ground falls across the site. It decides whether the floor is cut into the slope, built up, or stepped. Measure it along the length and across the width, as described below.

Farm building measuring checklist
MeasureFrom / toWhy we need it
A: length and widthPegged corners, both sides, both ends and both diagonals; say inside or outsideSets the footprint, the bays and the number of frames
B: eaves heightFinished yard level at the wall up to the roof line; check against your tallest machineFixes the column length and the clear height
C: doorsClear opening width and height, which wall, which endSets the opening frames and the space for sliding leaves
D: fall of the groundString line between pegs; reading at each peg and the distance between themDecides the floor level, the pads and any retaining
Distance to protected buildingNearest point of the building to the curtilage of the houseClass A bars a livestock building within 400 m
Distance to roadEdge of the metalled surface to the nearest part of the buildingClass A bars building within 25 m of a trunk or classified road
Distance to sleeping accommodationNearest point of the building to the nearest bedroomBuilding Regulations exemption needs 1.5 times the building height
Access widthNarrowest point of gateway and trackLorries and a crane must get in

Swipe the table sideways to see every column.

The six photos

Take the site from each corner, standing back far enough to show the pegs and the ground around them.

Photograph the ground where the building will stand, close in, with a tape or a spade handle in the frame for scale. Soft ground, old hardcore, a filled pit or standing water all change what your engineer asks for in the foundations, and we cannot see them from a satellite picture.

Photograph the access: the gateway, the track, and any overhead lines across them. Lorries bring the steel and the sheets, and a crane may lift the frame. Tell us the narrowest point.

Photograph any building it stands beside, including the side that faces the new one. Then photograph anything in the way: drains, trees, cables, a water main, a tank. Last, draw what you want on paper and photograph that. It need not be neat. A sketch with a few figures answers more than a page of description.

Measuring a fall

You do not need a surveyor for this. Drive a peg at the high end of the footprint and another at the low end, in line. Tie a string between them and pull it tight. Hang a line level on the string, or hold a long spirit level against it, and raise or lower the string at the low peg until it reads level. Then measure from the string down to the ground at each peg. The difference between the two readings is the fall. Write it down together with the distance between the pegs, because a fall means nothing without its length.

Do it along the length and again across the width, with a middle peg if the ground bulges. A laser level does the job faster.

Distances that decide the planning route

Measure these on the ground or on a map, because they decide whether the building can go ahead without a full planning application. For a livestock building under Class A of Part 6, the order says it must not be within 400 metres of the curtilage of a protected building. Measure from the nearest point of your building to the boundary of the house or other protected building, not to its wall.

The same class does not allow any part of the development within 25 metres of a metalled part of a trunk road or classified road. Measure to the edge of the surfaced road, not to the fence or the hedge. Height is limited to 12 metres, or 3 metres within 3 kilometres of an aerodrome; if you are near one, say so.

The Building Regulations exemption for agricultural buildings asks for no point of the building to be nearer to sleeping accommodation than one and a half times its height. Measure to the nearest house, caravan or bunkhouse. Your council makes the planning decision; we only draw the distances.

What not to measure

Leave the structural sizes to your engineer and to us. You do not need to measure foundation depths, purlin spacings, sheet laps, gutter falls or the frame. We work these out from your four sizes and the engineer's design, and we check clashes and fit on the model.

What happens after you send it

We check the sizes and photos first. If something is missing or does not add up, we reply within one working day and say what it is, before you pay for a pack that cannot be drawn. Once the pack starts, it is drawn from one 3D model of your building on your site, and every sheet follows from that model.

Questions

How do I measure the size of a farm building I want?

Peg the four corners of the footprint and measure both long sides, both ends and both diagonals. Matching diagonals mean it is square. Say whether your figures are inside clear space or outside the cladding. Then measure the height to the eaves from the finished yard level, and the clear opening of each door.

How do I find the fall across my site without a level?

Tie a string between two pegs, one at each end of the footprint, and make it level with a line level or a long spirit level. Measure from the string down to the ground at each peg. The difference is the fall. Write it down with the distance between the pegs, and repeat across the width.

How far from a house can I build a livestock shed?

For Class A of Part 6, the order says a livestock building must not be within 400 metres of the curtilage of a protected building. Measure from the nearest point of the new building to that boundary. Whether a particular building counts as protected is a question for your council.

Do I need to measure the foundations or the steel?

No. Foundation depths and steel sizes come from your engineer. We draw the frame, pads, sheets and fixings from your four sizes and photos. If you measure the access, the fall, and the distances to the road and to the house, we can show the planning route on the site plan.

Can I send you a sketch instead of a drawing?

Yes. A pencil sketch with the main sizes written on it, photographed flat in good light, is enough for us to start. Add the photos of the site from each corner and the ground where the building will stand. We check it and reply within one working day if anything is missing.

Sources

Read on the published page. These guides are for England unless they say otherwise, and explain the documents: your council, building control body and engineer decide your job.

  1. The Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 6, Class A, A.1(i)“within 400 metres of the curtilage of a protected building”
  2. The Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 6, Class A, A.1(h)“within 25 metres of a metalled part of a trunk road or classified road”
  3. The Building Regulations 2010, Schedule 2, Class 3 (agricultural buildings), para 2(b)“one and a half times its height from any point of a building”
  4. JPA Design: Farm buildings design pack, What we need from you“The length and width you want”