Trade/Structural steelwork/Erection and lift plans

Erection sequences and lift plans

The frame put up in stable stages, and every lift planned: the piece, its weight and centre of gravity, the sling legs and the hook height.

Erection sequences and lift plans

3D modelFrom sample project U7, rendered from the model.

What it is

The erection sequence starts from a stable box and grows from it, stage by stage, so the frame stands up at every step. Every lift is listed in order with its weight, and the heaviest and hardest are drawn as lift sheets.

The lifting plan stays the appointed person’s; our sheets give them the numbers from the model.

Sizes and options

As we draw it. Every size is set to your job.

StagesStable boxes, stage by stage
LiftsWeight, centre of gravity, sling legs, hook height
RegisterEvery lift in erection order

Worth knowing

The appointed person owns the lift plan.

BCSA's guide on site lifting says the appointed person is responsible for establishing and documenting safe systems of work for specific lifting operations. A drawing office supplies data, not the plan.

Source: BCSA Publication No. 47/09, Guide to the Management of Site Lifting Operations, clause 4.3

The detail

How it is made, fitted and priced, and what to tell us.

An erection sequence starts from a stable box and grows from it. In our largest sample, a 120 x 60 m distribution centre, there are ten stages, each drawn with the new steel in one colour, earlier stages in grey and later stages ghosted. Each stage notes the temporary bracing it needs and the connections made before the crane lets go. On a 448 x 192 m cross-dock, four phases, 84 stages and 153 lots opened with a braced pair of bays each time, so the structure always stood without help.

The lift list is what a crane operator and slinger actually use. The sample has 578 lifts in erection order, sorted into seven types: main rafter pairs, wing pairs, columns, posts, beams and bracing, purlin bundles and floor steel. Every lift has the piece mark, its weight, its centre of gravity, the lift points and the hook height needed. Weights are the model plus 3 percent, our allowance. Sling legs are laid out at 45 degrees or steeper, again our layout, so the numbers are a starting point for the lifting contractor.

The lifting plan itself belongs to the appointed person. BCSA publication 47/09 says the AP is responsible for establishing and documenting safe systems of work for specific lifting operations. So our sheets fill in the rows that come from the model, such as weights, positions and sequence, and leave the crane, the ground and the sling ratings blank for the AP. Sling working load limits and mode factors are the AP's, from the sling maker's certificate.

Plans change with the programme, not the steel. A different crane position, a later delivery or a wind hold changes the order. Because the lists come from the model, changes are re-run in minutes. Tell us the structure and mark list, where the crane can stand, the delivery gates, the programme dates, and who the appointed person is.

More views

Renders and sheets from our sample projects: made-up jobs, modelled and drawn the way a real one is.

U7-ER-40 Lift schedule and lift plan data
U7-ER-40Lift schedule and lift plan data
U7-ER-41 Lift A: main rafter pair, 30 m span
U7-ER-41Lift A: main rafter pair, 30 m span

Is it right for you?

Good for

  • Steel erectors
  • Main contractors

Not for

  • Choosing the crane or signing off the lifting plan: that is the appointed person's

What the drawings show

  • Stable-box erection stages, with the stage steel highlighted
  • Lift list in erection order: mark, weight, centre of gravity, hook height
  • Worst-case lift sheets with sling legs, angles and lift points
  • Columns shown laid out, tailed up and plumb
  • Fixing-down and the connections made at each stage

Questions

Who is responsible for the lifting plan?

The appointed person, under BS 7121 and the Lifting Operations and Lifting Equipment Regulations. BCSA 47/09 describes the AP as responsible for establishing and documenting safe systems of work for specific lifts. Our drawings give the AP the weights and sequence from the model; they do not replace the plan.

What is a stable box in steel erection?

A braced bay, or group of bays, that stands up by itself without cranes or props, to which further frames are added in order. Each stage extends it. It keeps the structure stable as it grows and gives the erector a safe place to start from.

Can you choose the crane for us?

No. The crane choice depends on the ground, the radius and the lifting contractor's charts. We give you the heaviest lifts, their positions and the hook heights, so the contractor or AP can choose and check a crane against them.

What do you need to plan erection stages?

The marked model, or the engineer's drawings; the site access and the position of any crane; the delivery order and the programme. If a part must be stable early, such as a lift core, tell us so we begin there.

Send the drawings.

Send the drawings and get a fixed price back within 4 working hours (Mon-Fri, 8 am-6 pm).

Not ready to send drawings? Ask for the full sample pack for your type of work, or a call back, with the form.

Big files: paste a WeTransfer, Dropbox or Google Drive link, or send them when we reply.

Thanks, that’s with us.

We use your details only to answer you: privacy, terms.